School Name | Project Description | Start Date | Completion Date | Percent Complete |
A K Wigg PS | Electrical Upgrade | 2022/09/01 | 2024/08/31 | 100% |
A K Wigg PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
A N Myer SS | HVAC System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
A N Myer SS | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
A N Myer SS | Electrical Upgrade | 2023/09/01 | 2024/08/31 | 100% |
A N Myer SS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
A N Myer SS | Lighting Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Applewood PS | Electrical Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Applewood PS | Lighting Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Burleigh Hill PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Caistor Central PS | HVAC System Upgrade | 2021/09/01 | 2024/08/31 | 100% |
Caistor Central PS | Wall Finishes | 2023/09/01 | 2024/08/31 | 100% |
Carleton PS | Interior Renovations | 2022/09/01 | 2024/08/31 | 100% |
Carleton PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Carleton PS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Carleton PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Carleton PS | Lighting Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Central PS / Former Grimsby SS | Plumbing Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Central PS / Former Grimsby SS | Roof Replacement | 2023/09/01 | 2024/08/31 | 100% |
Central PS / Former Grimsby SS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Cherrywood Acres PS | Fire Protection Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Dalewood PS | Accessibility Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Dalewood PS | Fences & Gate Replacement | 2023/09/01 | 2024/08/31 | 100% |
Dalewood PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Dewitt Carter PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Dewitt Carter PS | Interior Renovations | 2022/09/01 | 2024/08/31 | 100% |
DSBN Academy | Wall Foundation | 2022/09/01 | 2024/08/31 | 100% |
DSBN Academy | Wall Finishes | 2023/09/01 | 2024/08/31 | 100% |
DSBN Academy | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
DSBN Academy | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
E I McCulley PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
E I McCulley PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
E L Crossley SS | Sanitary Sewer Upgrade | 2022/09/01 | 2024/08/31 | 100% |
E L Crossley SS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
E L Crossley SS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Eden HS | Paving & Resurfacing | 2022/09/01 | 2024/08/31 | 100% |
Eden HS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Eden HS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Eden HS | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
Eden HS | Plumbing Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Eden HS | Plumbing Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Edith Cavell PS | Accessibility Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Edith Cavell PS | Fences & Gate Replacement | 2023/09/01 | 2024/08/31 | 100% |
Ferndale PS | HVAC System Upgrade | 2021/09/01 | 2024/08/31 | 100% |
Ferndale PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Ferndale PS | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
Forestview PS | Plumbing Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Garrison Road PS | Storm Sewer Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Glendale PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Glendale PS | Plumbing Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Glynn A Green PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Gordon PS | Storm Sewer Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Gordon PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Gordon PS | Plumbing Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Governor Simcoe SS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Governor Simcoe SS | Interior Renovations | 2022/09/01 | 2024/08/31 | 100% |
Governor Simcoe SS | HVAC System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Gracefield PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Grapeview PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Grapeview PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Grapeview PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Greendale PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Greendale PS | Accessibility Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Greendale PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Greendale PS | Window Replacement | 2023/09/01 | 2024/08/31 | 100% |
Greendale PS | Interior Doors | 2023/09/01 | 2024/08/31 | 100% |
Greendale PS | Wall Finishes | 2023/09/01 | 2024/08/31 | 100% |
Greendale PS | Fences & Gate Replacement | 2023/09/01 | 2024/08/31 | 100% |
Harriet Tubman PS | Wall Foundation | 2023/09/01 | 2024/08/31 | 100% |
Heximer Avenue PS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Heximer Avenue PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Jacob Beam PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Jacob Beam PS | Paving & Resurfacing | 2022/09/01 | 2024/08/31 | 100% |
James Morden PS | Fire Protection Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Jeanne Sauve PS | Electrical Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Jeanne Sauve PS | Clock & PA System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Jeanne Sauve PS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Jeanne Sauve PS | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
John Brant PS | Wall Foundation | 2023/09/01 | 2024/08/31 | 100% |
John Marshall PS | Fire Protection Upgrade | 2022/09/01 | 2024/08/31 | 100% |
John Marshall PS | Accessibility Upgrade | 2023/09/01 | 2024/08/31 | 100% |
John Marshall PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Kate S Durdan PS | HVAC System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Laura Secord SS | Interior Renovations | 2022/09/01 | 2024/08/31 | 100% |
Lincoln Centennial PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Lincoln Centennial PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Lockview PS | Lighting Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Lockview PS | Roof Replacement | 2023/09/01 | 2024/08/31 | 100% |
Lockview PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Martha Cullimore PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
McKay PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
McKay PS | Paving & Resurfacing | 2022/09/01 | 2024/08/31 | 100% |
Nelles PS | Lighting Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Nelles PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Oakridge PS | Fences & Gate Replacement | 2023/09/01 | 2024/08/31 | 100% |
Oakridge PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Oakridge PS | Wall Foundation | 2023/09/01 | 2024/08/31 | 100% |
Oakwood PS | Sport Playing Field Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Ontario PS | Accessibility Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Ontario PS | Interior Doors | 2023/09/01 | 2024/08/31 | 100% |
Ontario PS | Fences & Gate Replacement | 2023/09/01 | 2024/08/31 | 100% |
Ontario PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Ontario PS | HVAC System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Parnall PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Parnall PS | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
Parnall PS | Paving & Resurfacing | 2023/09/01 | 2024/08/31 | 100% |
Peace Bridge PS | Clock & PA System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Peace Bridge PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Peace Bridge PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Peace Bridge PS | Lighting Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Pine Grove PS | Site Drainage Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Pine Grove PS | Wall Finishes | 2023/09/01 | 2024/08/31 | 100% |
Plymouth PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Plymouth PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Port Colborne HS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Port Colborne HS | Roof Replacement | 2023/09/01 | 2024/08/31 | 100% |
Port Colborne HS | Security Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Port Weller PS | Site Drainage Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Prince of Wales PS (Thorold) | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Prince of Wales PS (Thorold) | Clock & PA System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Princess Margaret PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Princess Margaret PS | Interior Renovations | 2022/09/01 | 2024/08/31 | 100% |
Princess Margaret PS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Princess Margaret PS | Wall Finishes | 2023/09/01 | 2024/08/31 | 100% |
Princess Margaret PS | Clock & PA System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Richmond Street PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
River View PS | Fire Protection Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Ross PS | Sanitary Sewer Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Senator Gibson PS | HVAC System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Senator Gibson PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Senator Gibson PS | Wall Foundation | 2023/09/01 | 2024/08/31 | 100% |
Simcoe Street PS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Simcoe Street PS | Wall Finishes | 2023/09/01 | 2024/08/31 | 100% |
Simcoe Street PS | Wall Foundation | 2023/09/01 | 2024/08/31 | 100% |
Simcoe Street PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Sir Winston Churchill SS | Interior Doors | 2022/09/01 | 2024/08/31 | 100% |
Sir Winston Churchill SS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
Smith PS | Clock & PA System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Smith PS | Lighting Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Smithville PS | Electrical Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Smithville PS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Smithville PS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
St Catharines Collegiate SS | Sport Playing Field Upgrade | 2022/09/01 | 2024/08/31 | 100% |
St Catharines Collegiate SS | Security Upgrade | 2023/09/01 | 2024/08/31 | 100% |
St Davids PS | Plumbing Upgrade | 2023/09/01 | 2024/08/31 | 100% |
St Davids PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Stamford Collegiate SS | Lighting Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Stamford Collegiate SS | Roof Replacement | 2023/09/01 | 2024/08/31 | 100% |
Steele Street PS | Wall Finishes | 2023/09/01 | 2024/08/31 | 100% |
Stevensville PS | Locker Upgrades | 2023/09/01 | 2024/08/31 | 100% |
Stevensville PS | Roof Replacement | 2023/09/01 | 2024/08/31 | 100% |
Stevensville PS | Clock & PA System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Thorold SS | HVAC System Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Thorold SS | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
Thorold SS | Plumbing Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Valley Way PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Welland Centennial SS | Interior Renovations | 2023/09/01 | 2024/08/31 | 100% |
Wellington Heights PS | Roof Replacement | 2023/09/01 | 2024/08/31 | 100% |
Westdale PS | Electrical Upgrade | 2022/09/01 | 2024/08/31 | 100% |
Westdale PS | Interior Renovations | 2022/09/01 | 2024/08/31 | 100% |
Westdale PS | Fences & Gate Replacement | 2023/09/01 | 2024/08/31 | 100% |
Westlane SS | Sport Playing Field Upgrade | 2021/09/01 | 2024/08/31 | 100% |
Westlane SS | HVAC System Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Westmount PS | Floor Finishes | 2023/09/01 | 2024/08/31 | 100% |
William H Merritt PS | Fire Protection Upgrade | 2023/09/01 | 2024/08/31 | 100% |
Woodland PS | Roof Replacement | 2022/09/01 | 2024/08/31 | 100% |
Woodland PS | Electrical Upgrade | 2023/09/01 | 2024/08/31 | 100% |